A contractor who visits every four weeks returns on the same weekday. One who visits every calendar month can arrive on another weekday but retains the specified day number where it exists. Start by identifying which promise governs the service, before listing either set of dates.
A four-week interval contains twenty-eight dates. Several calendar months contain more. A technician who starts at the end of April can gradually see the appointment move earlier in the month under a four-week recurrence. A monthly schedule needs a separate note if it should always use the final date rather than the original day number.
Use repeat calendars to reproduce the main comparisons.
Work from the commitment made to the people using the equipment
When testing a timetable, display the next few nominal dates for both rules. Then add a column for booked work and the reason for an exception. Preserve the nominal series even if an individual inspection moved to accommodate access.
Pros and cons of the approach
Pros. A weekly pattern keeps staffing on one named weekday. An anchored monthly pattern fits agreements defined on calendar month days.
Cons. Either schedule can collide with a closure or a booking. Applying one rule after an exception can drift if the original anchor was discarded.
Ask whether the maximum time between actual checks or the nominal monthly appointment is the controlling constraint.
Maintenance schedules from the same anchor
The following examples compare calendar months and equal four-week steps. Compare intermediate occurrences, not just the last date on the sample history. A single agreeable first month can hide a later difference.
Series beginning 30 April 2026
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
| Applied choice | Computed value |
|---|---|
| Fourth occurrence, monthly | 30 July 2026 |
| Fourth occurrence, every four weeks | 23 July 2026 |
The first date belongs to both schedules. The third date on the monthly pattern is Tuesday · 30 June 2026 and the third on the four-week pattern is Thursday · 25 June 2026. These are useful interim checks before an organiser publishes the full list.
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Series beginning 1 May 2026
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Fourth occurrence, monthly. 1 August 2026. Fourth occurrence, every four weeks. 24 July 2026.
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
The first date belongs to both schedules. The third date on the monthly pattern is Wednesday · 1 July 2026 and the third on the four-week pattern is Friday · 26 June 2026. These are useful interim checks before an organiser publishes the full list.
Series beginning 31 May 2026
Fourth occurrence, monthly. 31 August 2026. Fourth occurrence, every four weeks. 23 August 2026.
The first date belongs to both schedules. The third date on the monthly pattern is Friday · 31 July 2026 and the third on the four-week pattern is Sunday · 26 July 2026. These are useful interim checks before an organiser publishes the full list.
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Original anchor 31 May 2026
The first record remains before the next whole-month anniversary. It leaves the anchor at 31 August 2026. The second lands on the anniversary itself and leaves 0 additional days. This change occurs even if both endpoints appear inside the same named month in a report.
- Through 29 September 2026 · 3 completed months and 29 extra days
- Through 30 September 2026 · 4 completed months
Keep 2026-05-31 as the original date when checking a future anniversary. Starting from a date clamped to the end of another month can keep the wrong day after returning to a longer month.
Compare calendar lengths of 121 and 122 days independently of the completed-month count.
Series beginning 31 May 2026
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
| Applied choice | Computed value |
|---|---|
| Fourth occurrence, monthly | 31 August 2026 |
| Fourth occurrence, every four weeks | 23 August 2026 |
The first date belongs to both schedules. The third date on the monthly pattern is Friday · 31 July 2026 and the third on the four-week pattern is Sunday · 26 July 2026. These are useful interim checks before an organiser publishes the full list.
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Series beginning 22 May 2026
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Fourth occurrence, monthly. 22 August 2026. Fourth occurrence, every four weeks. 14 August 2026.
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
The first date belongs to both schedules. The third date on the monthly pattern is Wednesday · 22 July 2026 and the third on the four-week pattern is Friday · 17 July 2026. These are useful interim checks before an organiser publishes the full list.
Records to compare before using this method
Compare intermediate occurrences, not just the last date on the sample history. A single agreeable first month can hide a later difference.
| Recorded example | First setting | First result | Comparison setting | Comparison result |
|---|---|---|---|---|
| Series beginning 31 May 2026 | Fourth occurrence, monthly | 31 August 2026 | Fourth occurrence, every four weeks | 23 August 2026 |
| Original anchor 30 June 2026 | Through 29 October 2026 | 3 completed months and 29 extra days | Through 30 October 2026 | 4 completed months |
| Series beginning 30 June 2026 | Fourth occurrence, monthly | 30 September 2026 | Fourth occurrence, every four weeks | 22 September 2026 |
| Series beginning 15 July 2026 | Fourth occurrence, monthly | 15 October 2026 | Fourth occurrence, every four weeks | 7 October 2026 |
| Series beginning 31 August 2026 | Fourth occurrence, monthly | 30 November 2026 | Fourth occurrence, every four weeks | 23 November 2026 |
| Original anchor 30 September 2026 | Through 29 January 2027 | 3 completed months and 30 extra days | Through 30 January 2027 | 4 completed months |
| Series beginning 31 October 2026 | Fourth occurrence, monthly | 31 January 2027 | Fourth occurrence, every four weeks | 23 January 2027 |
For a rescheduled visit, retain the date initially due and the date completed. Keep whichever one governs a later deadline according to the written maintenance plan.
Keep a clear calendar for an exception
For a rescheduled visit, retain the date initially due and the date completed. Keep whichever one governs a later deadline according to the written maintenance plan.
Series beginning 17 November 2026
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
| Applied choice | Computed value |
|---|---|
| Fourth occurrence, monthly | 17 February 2027 |
| Fourth occurrence, every four weeks | 9 February 2027 |
The first date belongs to both schedules. The third date on the monthly pattern is Sunday · 17 January 2027 and the third on the four-week pattern is Tuesday · 12 January 2027. These are useful interim checks before an organiser publishes the full list.
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Series beginning 31 January 2027
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Fourth occurrence, monthly. 30 April 2027. Fourth occurrence, every four weeks. 25 April 2027.
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
The first date belongs to both schedules. The third date on the monthly pattern is Wednesday · 31 March 2027 and the third on the four-week pattern is Sunday · 28 March 2027. These are useful interim checks before an organiser publishes the full list.
Original anchor 28 February 2027
The first record remains before the next whole-month anniversary. It leaves the anchor at 28 May 2027. The second lands on the anniversary itself and leaves 0 additional days. This change occurs even if both endpoints appear inside the same named month in a report.
- Through 27 June 2027 · 3 completed months and 30 extra days
- Through 28 June 2027 · 4 completed months
Keep 2027-02-28 as the original date when checking a future anniversary. Starting from a date clamped to the end of another month can keep the wrong day after returning to a longer month.
Compare calendar lengths of 119 and 120 days independently of the completed-month count.
Series beginning 31 March 2027
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
| Applied choice | Computed value |
|---|---|
| Fourth occurrence, monthly | 30 June 2027 |
| Fourth occurrence, every four weeks | 23 June 2027 |
The first date belongs to both schedules. The third date on the monthly pattern is Monday · 31 May 2027 and the third on the four-week pattern is Wednesday · 26 May 2027. These are useful interim checks before an organiser publishes the full list.
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Series beginning 28 April 2027
A real event can move for a venue or public holiday. Retain the nominal occurrence and use a documented exception if the series should keep the original anchor after the change.
Fourth occurrence, monthly. 28 July 2027. Fourth occurrence, every four weeks. 21 July 2027.
Four weeks is 28 calendar dates. A monthly rule chooses the destination month first and only adjusts the day when the original day is unavailable.
The first date belongs to both schedules. The third date on the monthly pattern is Monday · 28 June 2027 and the third on the four-week pattern is Wednesday · 23 June 2027. These are useful interim checks before an organiser publishes the full list.
Questions readers may need to resolve
What happens to a weekly pattern after February?
Four-week movement follows twenty-eight civil dates in every season. A leap date can change the day-of-month label without changing the weekday.
Why is the starter date listed as the first occurrence?
The schedule already includes that committed appointment. Counting four entries means three later moves.
Can I schedule precisely the last Friday each month?
Use a last-weekday rule month by month. Equal four-week steps may find an earlier Friday.
Does a rescheduled inspection change the next visit?
That depends on which anchor the plan specifies. An overdue inspection and the date it was originally due can have different roles.
Can delays become more frequent on a different weekday cycle?
Check each nominal occurrence against real access hours and closed dates. Counts alone do not establish availability.
Is a monthly cycle always longer than four weeks?
It can equal four weeks in some short February examples. Other calendar month movements can be longer depending on the original and destination dates.
Should an appointment include a time zone?
Yes if it is a timed calendar event. The nominal civil date sequence does not establish a local hour or its offset.
How can I tell which alternative the team prefers?
Check what was actually agreed, such as a fixed weekday or a monthly due date, then compare the draft dates to the venue timetable.